Plan issues and releases ​

Use this guide to set a target milestone, apply the repository's existing labels, and reconcile changes that actually shipped. Milestones and labels describe plans; they do not show that work was implemented, published, or deployed.

This is the same planning mechanism used for the 0.x product line. The component manifest and changesets remain the versioning mechanism; issue metadata does not publish packages or deploy workloads.

Before you begin ​

You need access to the repository's issues, pull requests, milestones, and labels. Authenticate the GitHub CLI before using the commands below. This guide changes repository planning metadata; it does not authorize package publication, cloud access, migrations, or deployment.

Choose a target release ​

Give every scheduled issue and its pull request the same version milestone, such as v1.0.7. Use the next unreleased patch for repairs. Group later capabilities into ordered, coherent version milestones rather than putting all remaining work under the initial release.

There is no fixed issue quota. A small repair release can contain one issue; a larger capability release can contain several related issues. Choose a batch that can be implemented, reviewed and tested together. Describe the outcome and prerequisite order in the milestone. Do not set a due date unless one has been agreed.

Use the earliest suitable unreleased milestone when the target is not yet clear. Do not choose an old open milestone just because its version is lower: publication records and unfinished validation work can remain open after shipping. If the work is genuinely deferred or not scheduled, leave its milestone unset and apply release:backlog.

powershell
gh api --paginate "repos/sabbour/agentweaver/milestones?state=all&per_page=100"
gh issue edit <issue-number> --repo sabbour/agentweaver --milestone <version>
gh pr edit <pr-number> --repo sabbour/agentweaver --milestone <version>

A milestone is a target, not an instruction to start work. Keep dependency order and existing implementation ownership. A partly implemented prerequisite is not complete because it has a target version. Finish the required prerequisite before dependent work can ship. Move the target if the prerequisite misses the cut.

Apply the existing labels ​

Use the existing repository labels. Do not create labels for each version or use a programme label instead of a milestone.

Label familyMeaning
type:*Use one applicable type: feature, bug, spike, chore, docs or epic.
area:*Name the affected product surface, such as api, web, workflows, backlog, runtime-resilience, observability, infra or testing. Several areas are allowed.
priority:p0A release blocker.
priority:p1Work in the current implementation batch.
priority:p2Work queued after the current batch.
go:yesThe scope is ready for implementation, subject to its prerequisites.
go:needs-researchInvestigation is still needed.
go:noThe work is not being pursued.
status:in-progressImplementation is actually in progress.
status:testingValidation is actually in progress.
release:blockingThe work blocks the release or its required checks.
release:backlogThe work has no scheduled release target.

Use at most one label within each of type:, priority:, go: and release:. Use the status that is true now; a planned issue is not in progress. Remove stale status labels when the activity ends. Closure, not a new shipped-status label, records completed issue work.

The older release:v* version labels are not maintained release targets. Remove them when replanning an issue. Keep historical labels on unrelated issues unchanged. The old bug, enhancement and workstream:* labels are also legacy names; use the corresponding type:* and area:* names for new work.

Understand the shared automation ​

GitHub issues and labels belong to the repository, not to a branch. Issue forms and issue-event workflows run from the repository's default branch. The existing Squad Label Enforce workflow keeps the go:, release:, type: and priority: families mutually exclusive. It adds release:backlog when go:yes is applied without a release label, and removes release labels when go:no is applied.

That workflow does not use the milestone to decide whether work is scheduled. After applying go:yes to a scheduled issue, remove any automatically added release:backlog. Do not remove a genuine release:blocking label. A person must review area and status labels, milestone assignments, and release reconciliation. The label sync workflow manages shared labels; there is no milestone-enforcement workflow. Do not copy branch-specific issue workflows or assume CI checks the release plan.

Reconcile the release that actually shipped ​

The release manager creates the next version milestone at the release cut. Future capability milestones may be created earlier to make the sequence visible. Keep the descriptions focused on release outcomes; creating one does not authorize publication or deployment.

After a package or CLI release, compare its published versions and consumed changesets with the merged pull requests. Assign each shipped PR to the first published version containing its changes, and assign the issues that PR actually completed to that version. Do not move an unfinished parent issue just because one partial contribution shipped.

Check whether a merge commit is in the release tag's history:

powershell
git merge-base --is-ancestor <merge-commit> <release-tag>

Exit code zero means the commit is an ancestor. It does not show that the feature was enabled or deployed. Check the package or CLI release itself as well. A PR merged after the latest release tag belongs to the next planned milestone, not the last published one.

Move work that missed the cut to the next suitable milestone. Do not leave unshipped work on a closed milestone. Close the implementation milestone only after publication and reconciliation are complete and no required validation work remains. A published release with unfinished checks can retain an open milestone; explain the remaining work in its description.

Track release acceptance ​

Create one GitHub issue named Release acceptance: vX.Y.Z for each version milestone, and assign it to that milestone. Use this issue to track release acceptance, not implementation work. The milestone remains a target; reconcile actual shipment against published versions and source history.

At the release cut, compare merged pull requests in v1 history, component changesets and published versions, and the tracker. Include the representative integration project, focused API and/or UI scenarios for every new feature (including features whose implementation issues are closed), risk-based regression scenarios, and applicable archive, operating-system, installation, documentation, cleanup, and carried-forward checks. Do not infer coverage from open issues or pending changesets alone. Use the release acceptance checklist for the tracker fields and sign-off criteria.

Close implementation issues after merge ​

An implementation issue tracks source delivery. After its work is complete:

  1. Confirm that the pull request is merged and that its commit is in the target v1 history.
  2. Confirm that the merged pull request or pull request set completes the issue's full source scope. Keep any real implementation gap in a focused issue; do not close a partially completed issue.
  3. Move any remaining live-acceptance task to the matching release tracker. Keep the scenario and its required evidence there.
  4. Comment on the implementation issue with links to the merged pull request and tracker item.
  5. Close the implementation issue as completed manually, then verify that GitHub shows it as closed.

Pull requests target v1, while dev is the default branch. GitHub closing keywords do not close an issue when its pull request merges into v1; do not rely on Closes #… or similar keywords. Keep later acceptance updates on the release tracker and any focused repair issue. Do not keep a completed implementation issue open only for acceptance work.

Follow up on release gaps ​

Follow the component release reference and release operations guide for versioning, NuGet package publishing, direct GHCR image builds, and Kustomize deployment. Keep package publication, image publication, workload deployment, and release acceptance as separate records.

If a required acceptance check finds a defect, create or reuse a focused repair issue in the next unreleased patch milestone. Link the failed tracker item and its evidence to the repair issue. Keep the original implementation issue closed unless its closure was factually wrong. Record a corrected-source test as a new attempt; a merged repair or release tag alone does not show that a corrected workload is running. Use the approved release and deployment procedures for any corrected publication or deployment.

Verify the plan ​

Check that each scheduled issue and its pull request use the same target milestone, the labels match the current work, and no unfinished prerequisite is treated as complete. After a release, reconcile the published package or CLI version with the changesets and merged changes before closing the milestone.